If you use the Encore Parkway bridge over Ga. 400 in Alpharetta, better start making other plans. It’ll be closed next year from January to November as part of a road improvement project.

The North Fulton Community Improvement District, city of Alpharetta and state road and transportation officials are teaming up to widen a seven-tenths-of-a-mile stretch of Encore between Westside and Northpoint parkways. As part of that, the bridge is being demolished, replaced and upgraded to accommodate any future Ga. 400 widening.

The $12 million project will also include wider 14-foot travel lanes, bike lanes, sidewalks, landscaped buffers and a raised, landscaped median. The approximately 18-month upgrade process started earlier this fall and is set to finish up in 2017.

About the Author

Featured

The last Michelin Guide Awards ceremony took place at the Georgia World Congress Center on Monday, Oct 28, 2024.

Credit: Jenni Girtman